Skip to content
Programme update

584 primary healthcare centres completed; 190 remaining

· Mathan Nigeria Limited

Programme status as at 21 October 2026: 584 primary healthcare centres completed, with 190 remaining across six geopolitical zones..

Completed main hospital building of a primary healthcare centre
Completed main hospital building

Mathan’s programme covers the construction and equipping of Comprehensive Primary Health Care Centres across Nigeria’s 774 local government areas.

As at 21 October 2026, 584 centres had been completed, with 190 remaining across six geopolitical zones.

Delivery across the remaining sites

Subcontractors carry out building work on assigned sites. Mathan’s site supervisors inspect work daily, report progress weekly and confirm each phase before the next begins.

Each completed site closes with a completion certificate and handover documentation.

Explore the PHC programme for background, Mathan’s role and the four phases of delivery.

Back to publications & news